Hickory Creek Pump Station Modifications

Description

Project included construction of a 36’ x 34’ x 31-foot deep cast-in-place concrete pump station with stand-alone control building and stand-alone generator. The project also included installation of 2,500 LF of 30” forcemain from the new pump station up to and on the site of the Regional Wastewater Treatment Plant and construction of a compensatory storage area north of Hickory Creek.

Project details

  • Owner: Village of Frankfort
  • Location: Frankfort, IL
  • Design Engineer: Strand and Associates, Inc.